Advertisement





10:07
0
The Director, Centre for Petroleum, Energy Economics and Law, University of Ibadan, and President, Nigerian Association for Energy Economics, Prof. Adeola Adenikinju, in this interview with DAYO OKETOLA, laments the country’s low transmission capacity and advises the government on what to do
What impact do you think the proposed $3.07bn expenditure will have on power transmission in the country?
The decision to spend part of the proceeds from the sale of PHCN assets on transmission infrastructure is a very good one. This will facilitate the evacuation of electricity produced by the existing and future power plants, help to modernise the existing infrastructure that is considered weak and old and that contributes to the relatively high transmission losses and system failures in the country. Low investment in transmission infrastructure is one of the weak links in the electricity development programmes in the past. This, hopefully, will correct that problem.
Moreover, the government is in the best position to carry out this type of investment. However, it is important that the money is well spent to ensure that Nigerians get value for their money. It is important that the process is credible, transparent and open to give the right contractors the opportunity to handle the projects.
It is important to also mention that other aspects of the electricity supply process need attention. Both the generation and distribution segments still need considerable attention. The distribution segment is particularly important given the current huge technical and economic losses in that segment. Moreover, quite a large proportion of the population are yet to get the prepaid meters and still get what they refer to as ‘crazy bills.’ This too must be addressed.
The government’s programme must also give consideration to the rural areas. What is the plan to extend electricity to a large segment of the population where electricity access is currently less than 20 per cent?
Do you think the government will not play politics with the whole process?
The only way to ensure that the government does not play politics with this project is for it to preannounce a timeline for the implementation and give timely reports on progresses made and challenges faced to Nigerians.
Independent stakeholders should also be allowed to monitor the project. In fact, the government must put in place a post-privatisation plan to ensure that companies that acquired the privatised assets keep to the performance agreements and Nigerians get value for their money. The current trajectory of electricity prices as shown in the MYTO is on the high side due to the current huge economic and non-economic losses in the system. By cutting these losses, Nigerians should expect a steady decline in electricity prices in the medium term.
What advice do you have for the government to ensure that this does not become a failed project like many others before it?
The money must be kept in an escrow account that is wholly dedicated to the project. In addition, the contract process must be credible and transparent. Only contractors that have pedigree must be selected. Once the right contractors are chosen and they have the assurance that they will be paid, it becomes a lot easier to ensure that they deliver. However, when lackeys of government are chosen based on their political connections, then it will be difficult to give an assurance on performance.
Are you satisfied that the nation still generates less than 4,000 megawatts of power despite the government’s huge investments in the sector? 
I have said it before that it is rather a show of mediocrity for Nigeria to be generating less than 4,000MW of electricity for a population of more than 150 million people. When I was a Special Assistant to the Special Adviser to the President on Energy during former President Olusegun Obasanjo’s regime, I was a member of a group mandated to come up with the power requirement for Nigeria in order to be an industrialised country by 2030.
And when we did the analysis, we found that for Nigeria to be an industrialised country by 2030, at least the country would need to generate 120,000MW of electricity. The vision was that by 2007, we would have had 10,000MW; now, we are still around 4,000. This will even not be enough to power a state in the United States.


50% off Hosting for your Website at GoDaddy.com!
It's a BIG Deal! $5.99* .COM from GoDaddy.com!
It's a BIG Deal! $5.99* .COM from GoDaddy.com!
Host a site without stress on namecheap eApps|YOUR APP HOSTING PROVIDER
Submit your Website
Free webmaster resources including SEO Tools, Computer Glossary, Templates Sign up to BIGTIMEBUX today!

0 comments:

Post a Comment